Resource Loading Report in Spreadsheet format

1 reply [Last post]
Alfon Lyndon Joson
User offline. Last seen 7 years 27 weeks ago. Offline
Joined: 28 Mar 2004
Posts: 35
Groups: None
Hi,

can anyone help me on how to export resource loading report in spreadsheet format in P6?

regards

alfon

Replies

Dieter Wambach
User offline. Last seen 7 years 21 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Alfon
You’ll create a report out of the group "resource&role assignments" and don’t forget to select "Time distributed data". You’ll be guided by the wizzard. After you’ll have run the report, create a text file (*.csv) May be you’ll have to check for the separators - start with ";".
Regards