Calculating Man Hours in P6

B
Beth Spivey 👤 Member for 19 years 6 months
B
Beth Spivey 👤 Member for 19 years 6 months

Thank you all for your responses.



It was the type of duration I had assigned. I changed to fixed units/time and it corrected all my activities.



Again thanks!



Beth

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Beth

Did you have a look into your user preferences?

Edit --> User Preferences --> Calculations

For better knowledge, then try "Help"



Regards

Dieter

D
Duy Huynh 👤 Member for 18 years 2 months

Hi Beth,

Did you try this option: Tools>Recalculate Assignment Costs....



It will help your problem solved.



Duy.

B
Beth Spivey 👤 Member for 19 years 6 months

Ken,



Thanks for your response. My only concern is when we made major changes in resources I had to manually recalc and enter the manhours or completely remove and reassign which is very time consuming. And P3 would recalculate itself.



I am thinking P3 was much better.

K
Ken Barrett 👤 Member for 19 years 1 month

When you change your resource you might need to manually input the budgeted units / duration / budgeted units/time. When a resource is changed the units somtimes automatically revert to whatever you have as a default setting. Also if you go to the Assignments tab on the tool bar on the left hand side of the screen, it should have a list of all the resources you have in the schedule and their units (you may have to go to the column settings to add the columns that you need).

I hope this helps you out



Ken Barrett

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts