Showing numbers on Manpower Graph bars

I
Ijaz Ahmad 👤 Member for 19 years 11 months
A
arslan usmani 👤 Member for 19 years

Ijaz,



what we are doing is that from Resource assignment we transfer the data to Excel and plot the graph. This gives the room to plot the graphs on two vertical axis.



Cheers,



Arslan Usmani.

W
Waseem Saber 👤 Member for 21 years 6 months

Ijaz,



this question has been raised with Primavera, this should be covered in P7 version "fingers Crossed", if you are so desperate, i would advice to export the data to any db and present your schedules....... this is more userfriendly and more graphical options..



cheers



Waseem Saber

J
Johny Kesserwany 👤 Member for 18 years 9 months

Hi Ijaz,



It seems that we can’t !!! I already raised the issue with Primavera technical support and I wasn’t able to display the values on the bars....



regards

jk

Forum Sponsor

Top Posters

Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts