Display progress on target bar for P5

J
Jerry Lan 👤 Member for 19 years 10 months
A
Andrew Pearce 👤 Member for 25 years 1 month

I put up a similar posting earlier this year.

It is possible to overlay a %complete bar on a baseline bar, the problem is that the % bar is drawn starting on Actual start date, not on baseline start date as in P3.