Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P5 planned value labour units & earned value labour uni

1 reply [Last post]
Donovan Govender
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 20
Groups: None
I need to show a histogram with planned, actual & earned and scurves for the same in one profile,
my profile histogram shows my budget,baseline,and actual,but the scurves,I have the planned value labour units & earned value labour units ticked but is not showing,

Please help

Regards
Donovan

Replies

Rodel Marasigan
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Donovan,

Is your schedule resource? If not? then not possible. If resource then have you tick the cummulative or just By Date?

HTH