ACTIVITY STEPS REPORT FOR FEW WBS

2 replies [Last post]
Suresh Sankaranku...
User offline. Last seen 5 years 1 week ago. Offline
Joined: 30 Jul 2006
Posts: 77
Hi,
Anyone have any idea of How to generate a report of Activity steps for a particular WBS. All that i can see the impossibility is in the Filter there is no WBS parameter. Its a big drawback in P3E 3.5.1 Version. I donno whether you have any idea to achieve this. If you find any soluation pls let me know .

If we know how to create new parametre in Filter combo box this problem can be solved.

Thank you
Suresh

Replies

Dieter Wambach
User offline. Last seen 7 years 17 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Suresh

It’s just an idea (I have only P5 and P6 availabel):
New Report --> Group "Activities" --> Add sub area "Activity Steps" --> add required data items + some in reserve (to replace them using the editor with items you need but can’t achieve with the wizzard) --> filter by wbs.
Hope this will help.
Dieter
Patricia Le Clainche
User offline. Last seen 9 years 41 weeks ago. Offline
Joined: 18 May 2007
Posts: 86
Groups: None
Hello Suresh,

I do not ’play with Primavera’ at home, so it’s difficult at the moment to test. But one idea come to my mind. If it is not possible to filter on WBS, you could create a new project in a Simulation Space , that contains the particular WBS you want.

What do you think about it ?
Kindest regards.
Patricia