All,
I'm hoping for insight. I have an activity that has been locked in a baseline. I have created a lower level WBS within that same WBS which breaks the original baseline activity into smaller chunks of work - example - Install Pad Piers (original baseline activity) in the "concrete" WBS. I created a lower level WBS called "Pad Piers" and my activities are "Pad Pier #1, Pad Pier #2", etc. I have created steps on each of the "Pad Pier #1/#2, etc for progressing which gives me a % complete. I have pulled over to the Activity Chart the column "Performance % Complete" which shows a % complete for the WBS title bar which means as I progress the lower level "Pad Piers #1/#2" etc, the WBS bar will give me a % complete which is what I will use to progress the original one liner from the baseline "Install Pad Piers". My question is this - is there a way to have that original baseline activity be updated on it's % compelte form the lower level WBS.
I hope this makes sense lol......it's been a long day.
Any help appreciated!!
H
Replies