To Export Resource Histrogram from P3e to Excell

1 reply [Last post]
Minhas Shaikh
User offline. Last seen 13 years 26 weeks ago. Offline
Joined: 30 Mar 2007
Posts: 44
Hi Planners,
Can we export resource histrogram from p3e to excel. If yes please write down steps. and if no please explain if you can.
waiting for your reply.

Minhas

Replies

Roger Booth
User offline. Last seen 4 years 34 weeks ago. Offline
Joined: 26 Oct 2006
Posts: 74
Groups: None
Minhas
The only way I have managed to do this, is by creating a report that gives me resource hours per week or month, and then when you run the report instead of sending it to a printer, send it as an ASCII file using field delimiter as , and Text qualifier as " Save the file as a text file which excel can then read. Tidy up the data in the excel file and then either produce a graphical representation of the data or a spreadsheet.
To save all this though if you just want a resource histogram just set the print options to show a profile, Whichever resource is highlighted when you go to print will be shown on the profile