Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Smallest total float

5 replies [Last post]
KIAN GHADAKSAZ
User offline. Last seen 8 years 20 weeks ago. Offline
Joined: 25 Dec 2006
Posts: 12
Hi All,
I have a question about P3E-Ver.5 In schedule option there is an option "compute total float as :smallest of start float and finish float" As I know in P3,start float and finish float could be different based on "contiguous" and "interruptible" check mark in schedule option window,but in p3e-ver.05 I don’t know in which circumstance finish float and start float can be different.would you please help me if sombody know the answer.

Regards,

Replies

Khuong Do
User offline. Last seen 17 years 6 weeks ago. Offline
Joined: 1 Sep 2006
Posts: 38
Groups: None
Hi Kian!

I’m sorry. You are right. It seems that in this new version 5.0 Start float and finish float are the same in Interruptible activity and constraint activity.
I’ll check with some of my college and feedback you in case I find the answer.

Thanks
Khuong
KIAN GHADAKSAZ
User offline. Last seen 8 years 20 weeks ago. Offline
Joined: 25 Dec 2006
Posts: 12
Dear Khuong

Thanks for your consideration,by the way as I checked difference total float for activity that has suspend and resume dates and also for activity which has constraint,I couldn’t find any difference(as you know P3e calculates based on remaining early dates)would you please clarify the issue.

Regards
Niek Zonneveld
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
Kian,

It’s actually very simple: If one single activity has both SS and FS relationships, the start float and finish float can be different.

H.T.H.
Khuong Do
User offline. Last seen 17 years 6 weeks ago. Offline
Joined: 1 Sep 2006
Posts: 38
Groups: None
Hi Kian

Start and Finish float are usually the same, however they can be different in the following situations.

1. When using Suspend & Resume
2. When using constraints
3. Hammock/Level of Effort activities
4. WBS activities
5. Summary calculations that get their dates from detailed activity information

The easily seen situation is Level of effort activities. The first activity and last activity of LOE activity usually have different float. So the schedule option can bring into play now.

Thanks
Khuong
Dieter Wambach
User offline. Last seen 7 years 26 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Kian

This is a topic more for the purists. For a normal activity until today I wasn’t able to realize real difference. For WBS-Summary there are, but I don’t know why. I didn’t analyze float on WBS-summary activities, since it was not important for me. Others may know an answer.

Regards

Dieter

By the way, this is the area for old P3.