Top Down Estimating in P3e

Member for

13 years 10 months

I want to estimate MANPOWER that is required to complete a project: I have a plan with thousands of activities, duration, start and end dates but don't know how many resources do i require to complete it.

 

So how can i estimate it in Primavera 6 in Top Down Estimate? Please explain and i would really appreciate the snapshot/video tutorial for this.

Member for

18 years 9 months

Hi Emmanuel,

You open your project with the view "WBS". You click onto the detail tab "Budget log".

The first level is the project itself, the others are the different levels of the WBS. Now you enter the appropriate figures.

Later, after you planned your activities with workload*price/unit and the expenses you’ll be able to compare on any level if your plan corresponds to your budget.



Reards

Dieter

Member for

21 years 9 months

I want to estimate money at both EPS and WBS levels.

Kind regards.



Emmanuel

Member for

19 years 1 month

Hello Emannuel,



I would try to help you, but I need to know what you are

planning to do?



Do you want to make a "Top Down Estimate" in order to

compare your estimation with your schedule?

Which values do you want to estimate? (money, people, material? Anything else then money will be very difficult.)

Would you estimate the availiable money on the project and WBS-Level or also on EPS-Level?

Would you estimate the money in one block per EPS / Project / WBS or also by month?



Kind regards

Peter