James bid
User offline. Last seen 9 years 43 weeks ago. Offline
Joined: 8 Oct 2009
Posts: 50
Hi Guys,

I have three activities in my program that i want to remove the actual dates, suspend date and resume date.
For actual dates, i tried to remove the actual units, set OD to zero but still i can’t remove the actual date.
Hoping for your help.

Thanks

Replies

Rodel Marasigan
User offline. Last seen 6 weeks 5 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Christopher,
Change the actual units to 0 first before you can remove actual dates.
James bid
User offline. Last seen 9 years 43 weeks ago. Offline
Joined: 8 Oct 2009
Posts: 50
Thank you Rodel for immediate response.

I tried also to set the actual units to zero but still, \i can’t remove the actual date. Any other remedy?

Also, please help me to remove the suspend and resume date.

Regards.

Chris
Rodel Marasigan
User offline. Last seen 6 weeks 5 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Christopher,
To remove Suspend and Resume date, highlight suspend date and press delete on keyboard.

To remove Actual date go to Activity detail Resource tab and change to 0 all resources assigned then un-tick start date.

You can also use global change for both queries.

Best Regards,
Rodel
James bid
User offline. Last seen 9 years 43 weeks ago. Offline
Joined: 8 Oct 2009
Posts: 50
I got it.

Thanks Rodel for your help.

Chris