Percent Complete Type-Duration Type

1 reply [Last post]
Mike Reymort
User offline. Last seen 6 years 32 weeks ago. Offline
Joined: 24 May 2017
Posts: 7
Groups: None

I have been looking around for a good explanation on the percent complete type and duration type settings. I have a pretty good idea about how they work and when to assign what, but would love to have a direct explanation from someone who actually worked with them.

 

Thanks in advance,

 

Mike  

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

if you want to use earned value you have to use for percent complete however this does not update the remaining duration or your actual units so you can run a global change

where physcial % complete is greater than 0

then duration % complete = physical % complete

 

for duration type if you do not want you labor units determining your durations use fixed duration and units/time

if you want your durations determined by the resource then use fixed duration & units