Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera P3E/C version 5

3 replies [Last post]
Kevin Ton
User offline. Last seen 17 years 9 weeks ago. Offline
Joined: 7 Nov 2006
Posts: 11
Groups: None
Hello,

Has anyone ever experienced P3E/C very slow?

Recently, my project migrated from p3 to P3E/C with 8000 activities, whenever I made any change, it just took ages to finish?

Any suggestion would be very appreciated.

Replies

Kevin Button
User offline. Last seen 2 years 48 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
Just a thought, is the project rescheduling after you make a change? There is a scheduling option called ’Schedule automatically when a change affects dates’. This option is OK for small schedules but with 8000 activities I would have this switched off.

KB
Alex Wong
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Kevin

Are you using a networked P3e??
Sometime the network traffic is the bottle neck of the slow respond issue.
Talk to your IT helpdesk (Standard reply will be we do not have any issue with our intranet ^&*)
HTH

Alex
Check your PC’s virtual memory and adjust to maximum