Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P5-Top Down Estimation!

1 reply [Last post]
Suraj Bhatt
User offline. Last seen 10 years 4 weeks ago. Offline
Joined: 24 May 2004
Posts: 58
Groups: None
Hi!
I have a basic schedule with 4 levels of WBS.The activities in the 4th level are repetitive i.e. they repeat in each 4th level.
I wish to put the total resource for the 3rd level and use top down estimation to distribute it as per the activity duration.
E.g. If total resource for the 3rd level is 1500
I want TDE to distribute this 1500 into the lower WBS activity based on the activity durations.
Is this possible???
Thanks in advance
Regards
Suraj

Replies

David Kelly
User offline. Last seen 2 years 8 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Suraj,

Yes. You will need to set the estimation factor to the original duration. This is possible using global change, however it would be simpler if the global change that does this selects only activities at level 4 of the WBS - that way the TDE run can include the whole project, as activites not at level 4 will have an estimation factor of 0.

There is no way I know of automatically selecting "level 4" activities, perhaps an activity code could do this?