Histograms for Different Resources

5 replies [Last post]
Shahzad Sikandar
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
It is possible to view histogram for diffrenet resource in resource usage profile?

I meant to ask, i want to see comparision of differnt resource as a histoigram on each activity, cuz p3e only show resoule profile for single resouirce to be seen individually.

any comments, please
be appreciated.

thanks

Replies

Shahzad Sikandar
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
i have got that done now.
many thanks
Shahzad Sikandar
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
many thanks for your reply,
but there is no filter selection option under resource usage profile GRAPH OPtion, I am using Projection Management Software (P3e).
Kevin Button
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
You need to right click on the graph and select ’Resource Usage Profile Options’, where you need to set some filters and choose a colour for each filter output.

Cheers

Kevin
Shahzad Sikandar
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
but when you checked on staked histograme every thing disappeared.
Kevin Button
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
You could try using the Stacked Histogram, however a problem using this is that it shows individual resource usage based on the currently filtered activities rather than the selected activities.

HTH

Kevin