Hi there,
Need some help.
Scenario : Just came into a project, the activity codes were setup previously by my predecessor. Unfortunately, through the years, the values have been multiplying. Redundancies are evident. Need to clean up the mess.
In the company, SAP has been established with equipment tag nos built in it. During execution, SAP and P3e would have to work together. Ideally, the schedule should contain the same values of that in SAP to the exact format.
e.g. currently in SAP value is 45E-0501.
However in P3e value is 45E-501. When it should be the same.
Plan : To extract the values in SAP and import it into P3e Activity Codes (Global) as values via a spreadsheet with the description as well.
Problem : Tried it before in Ver 4.1, could not find a way to do it. Now I have ver 5.0, still no idea. Only way so far is to input it one by one.
So any bright ideas ? enlighten me.
Thanking in advance.