Overall Physical %

5 replies [Last post]
rabbani wgl
User offline. Last seen 16 years 13 weeks ago. Offline
Joined: 9 May 2006
Posts: 15
Groups: None
Hello Experts,
Can you please tell how to show overall Physical% complete for a project in P3 e/c... the way it shows when the % complete type is Duration % Complete.

Thanks
Rabbani

Replies

Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Thanks Julie,

Now it is clear to me.

Regards.
Julie Scully
User offline. Last seen 16 years 42 weeks ago. Offline
Joined: 9 Nov 2005
Posts: 25
Marcio

From the bulletin...

"At the summary level, the Performance % complete is calculated as follows:

Performance % Complete = (BCWP * 100) / BAC

(Where the BCWP is the Budgeted Cost of Work Performed and the BAC is the Budget At Completion)

BCWP is calculated as Activity % Complete * Baseline Total Cost"

Cheers
Julie

Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Heelo Julie,

Do u know why Costs assingned is a condition? Why not units only?

Regards.
Julie Scully
User offline. Last seen 16 years 42 weeks ago. Offline
Joined: 9 Nov 2005
Posts: 25
Summarising the physical % complete is currently an enhancement request that Primavera are looking into. They have a workaround on the knowledgebase (bulletin # prim11292), but one of the conditions is having costs assigned to the activities.

HTH

Cheers
Julie
Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Hello Habbani;

Try to see what i wrote on BL Cost % Complete - Summary Roll-up here in Primavera Enterprise - Teamplay / P3e & P3ec category.

http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=21607

Hope it helps.

Regards.

Marcio Eduardo