P3e Database Mapping

2 replies [Last post]
Emma Seaton
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 16 Sep 2005
Posts: 55
Groups: None
Does anyone know which database field maps to the data date. I can find just about everything else in the Schema Documentation tables, but no data date to be found anywhere, have I just missed it or is it not there? I need it for a query in excel where I’ve linked up a spreadsheet to the P3e MSSQL database.

Cheers

Emma

Replies

Emma Seaton
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 16 Sep 2005
Posts: 55
Groups: None
Thanks Niek, that’s brilliant - I knew it had to be somewhere, I just wasn’t expecting it to be called ’recalc’ - I’d been looking for ’data’ or ’schedule’ date... I am very happy now!! :o)

Cheers,

Emma
Niek Zonneveld
User offline. Last seen 2 years 19 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
Emma,

last_recalc_date in the Project table.

H.T.H.

Niek.