Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

HOW CAN I MAKE CALENDER

16 replies [Last post]
tamer sayed
User offline. Last seen 15 years 38 weeks ago. Offline
Joined: 15 Feb 2006
Posts: 38
PLEASE HELP ME IN THIS CASE
I USE PRIMAVERA ENTERPRICE
AND THERE ARE DEFULT IN CALENDER IN SHEFT ( 6 DAYS × 8 HOURS )
I WANT TO CHANGE IT TO
7 DAYS × 24 HOURS
I ALREADY CHANGE IT TO NEW CALENDER BUT THE DURATION NOT CORRECT
AND THERE ARE CHECL MARK IN THE DEFULT SHEFT
PLEASE HELP ME
THANK YOU

Replies

tamer sayed
User offline. Last seen 15 years 38 weeks ago. Offline
Joined: 15 Feb 2006
Posts: 38
also i wark in net work ani i trayed many time to change hour per day to 24
but i can not
it is fixed on 8 hours per day
could you tell me what can i do
tamer sayed
User offline. Last seen 15 years 38 weeks ago. Offline
Joined: 15 Feb 2006
Posts: 38
if i want to change only one project what i will do
vito Kooij, van
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 8 Dec 2005
Posts: 12
Groups: None
correct!

tnx
Marcio Sampaio
User offline. Last seen 11 years 46 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
But remember ... doing it ... u will chenge all projects!!!
vito Kooij, van
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 8 Dec 2005
Posts: 12
Groups: None
to change "hours per time period" you need to be logged in as admin and go to [admin]>[admin preferences]> tab [time periods] then you can do what ever you want.

this is all! (see more ad nr: #11)
tamer sayed
User offline. Last seen 15 years 38 weeks ago. Offline
Joined: 15 Feb 2006
Posts: 38
COOULD YOU TELL ME HOW CAN I WILL CONTACT WITH ADMIN TO CHANGE DURATION
I WANT TO SEE
24= 1 DAY
BUT IN MY PROJECT
24 HOURS = 3 DAYS
THAT MEAN 8 DAYS PER DAY ONLY ( SHIFT = 8 HOURS )
AND I WANT SHIFT = 24 HOURS
I CHANGED CALENDER TO 24* 7
BUT THE SAME PROPLEM FACED ME
ALSO I DO DEFULT FOR MY CALENDER 24*7
BUT I FIND
24= 3 DAYS
THANK YOU
vito Kooij, van
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 8 Dec 2005
Posts: 12
Groups: None
the problem can be solved by chance settings in user preferences.

Actions> go to [edit]>[user preferences] tab[time units] then under [Durations format] and set unit of time to [Hour].

you will see now that od of 24 hrs = one day.

tis problem is caused by your settings in [units per time period] you can change it in admin pref’s (primavera use this as a conversion rule for calculate differend units back to hr’s. every project is calculated to hrs in the background of the database)

hope this is usefull.
greetz vito
Emma Seaton
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 16 Sep 2005
Posts: 55
Groups: None
Interesting to hear that someone else has the same problem with the durations when changing calendars. In my view the calendar selected should override all other time settings. Is this a fault that should be reported to Primavera, if not done already?
tamer sayed
User offline. Last seen 15 years 38 weeks ago. Offline
Joined: 15 Feb 2006
Posts: 38
DEAR /A LL
I already done all this steps but problem still .
I want to tell you problem in details
First I create new calendar 24*7 days and done new tasks with new calendar
Example :-
First task 24 hours ( that mean this will stay 1 day )
After that when I go to user preference to change hour to day
24 hours appear = 3 days ( that mean 1 days =8 hours )
This is problem
I create calendar 24 hours per day but system use default calendar 8 hours per day
This is problem
In another side I go to defult to set new calendar but problem still
24 hours = 3 days
And I want
24 hours = 1 day


Another problem original duration
When I create some steps and I want to see summation of all duration of this tasks in main original duration
But I found number in original duration is not correct
Could you solve me this problem
Thank you






Julie Scully
User offline. Last seen 16 years 37 weeks ago. Offline
Joined: 9 Nov 2005
Posts: 25
You also need to be aware of the global ’Time Period’ settings under ’Admin Preferences’. The duration entered (in days) is worked out (in hours) using the Admin Preferences and converted back to a duration using the activity calendar.

For example:
Global Time periods are set to 24h/d, 7d/wk etc.
No resources, activities are task dependent.

EXAMPLE 1 - 8hrs x 5d Calendar
Duration entered=5days=24*5=120hrs. Based on 8x5 the duration will be 15days, excluding weekends (120/8)
Start=20/2/06
Finish=10/3/06

EXAMPLE 2 - 10hrs x 7d Calendar
Duration entered=5days=24*5=120hrs. Based on 10x7 the duration will be 12days, including weekends (120/10)
Start=20/2/06
Finish=3/3/06

Hope this helps.
Cheers
Julie
Marcio Sampaio
User offline. Last seen 11 years 46 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Create a resource;

Create a resource shift with 1 shift 24 hrs;

Assign this resource to activities;

Actvity Type = Resource Dependent.

Think thats it, hope it works.

Regards.
Emma Seaton
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 16 Sep 2005
Posts: 55
Groups: None
I’ve found a similar problem. I have a calendar which is 10 hrs x 7 days and cannot get the durations to calculate properly (I get strange start and finish hours, with activities spread over 3.5 instead of 2 days, for example. I’ve tried changing the settings under User Preferences, but this doesn’t really work as it affects activities on other calendars, and of course it affects other projects.

Do I have to change other calendars elsewhere, such as WBS or project? None of which makes sense - surely if I specify a calendar to an activity it should override any defaults. It works fine when I use other calendars, such as for railway possessions which are often strange hours overnight at weekends!!

Looking forward to hearing from anyone!

Emma
tamer sayed
User offline. Last seen 15 years 38 weeks ago. Offline
Joined: 15 Feb 2006
Posts: 38
dear / Julie Scully
could you please tell me steps in detalies
i am new in primavera enterprice
and this case is very comflect
please tell me frist do that , second do that , third do that
also please tell me criteria in global change
thank you
Julie Scully
User offline. Last seen 16 years 37 weeks ago. Offline
Joined: 9 Nov 2005
Posts: 25
Tamer

You will need to assign this new 24x7 calendar as the default calendar for the project for new activities to automatically have it assigned. You will also need to change the calendar assigned to each of your existing activities; either by adding the calendar column to your view and filling down, or doing a global change.

Cheers
Julie
tamer sayed
User offline. Last seen 15 years 38 weeks ago. Offline
Joined: 15 Feb 2006
Posts: 38
i can not find any solution for my question
please tell me steps
thank you
Marcio Sampaio
User offline. Last seen 11 years 46 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Tamer,

See thread "WBS calendar"

Regards.