Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Earned value

1 reply [Last post]
niles luo
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 25 Nov 2005
Posts: 46
Groups: None
Dear All,

What is different among these options in p3e/c software when we calculating the earned value:

At Completion values and current dates,
budgeted values with planned dates,
budgeted values with current dates

It can be set in Admin Preferences dialog box,but I did not know the different.
Please tell with an example

cheer,
niles

Replies

Marcio Sampaio
User offline. Last seen 12 years 8 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Niles Luo;

1-Technique for computing performance percent complete:

- Activity % Complete: Choose to calculate earned value according to current activity completion percentages.

- Use WBS Milestones: Choose to calculate earned value by defining milestones at the WBS level and assigning a level of significance or weight to each of them. As progress occurs and you mark each milestone complete, the WBS element’s performance percent complete is calculated based on the weight of the milestone.

- 0/100 % Complete: Choose to calculate earned value as 100 percent only after the activity ends.

- 50/50 % Complete: Choose to calculate earned value as 50 percent after the activity starts and until the activity ends. After the activity ends, the activity’s earned value is 100 percent.

- Custom % Complete: Choose to calculate earned value as a percentage you specify. This percentage applies after the activity starts and until the activity ends. After the activity ends, the activity’s earned value is 100 percent.

2- Technique for computing Estimate To Complete (ETC)

- ETC = remaining cost for activity: Choose to calculate Estimate To Complete (ETC) values as the remaining cost to complete an activity (ETC = remaining units of activity * applicable resource rates).

- ETC = PF * (Budget at Completion – Earned Value Cost), where

- PF = 1: Choose to calculate Estimate To Complete (ETC) values as a Performance Factor (PF) of 1 multiplied by Budget At Completion (BAC) less Earned Value Cost .

- PF = 1/Cost Performance Index: Choose to calculate Estimate To Complete (ETC) values as a Performance Factor (PF) of 1 divided by the Cost Performance Index (CPI) .

- PF = 1/ (Cost Performance Index * Schedule Performance Index): Choose to calculate Estimate To Complete (ETC) values as a Performance Factor (PF) of 1 divided by the product of the Cost Performance Index (CPI) and Schedule Performance Index (SPI) .

- PF =: Choose to calculate Estimate To Complete (ETC) values as a Performance Factor (PF) you specify multiplied by Budget At Completion (BAC) less Earned Value Cost. If you choose this option, type a factor in the PF field.

3- Earned value calculation

When calculating earned value using a primary baseline use

- Budgeted values: Choose to use the primary baseline’s budgeted values for earned value calculations.

- At Completion values: Choose to use the primary baseline’s At Completion values for earned value calculations.

It was extracted from P3e HELP.

I don’t know if it is realy your doubt.

Best regards.

Marcio Eduardo
Rio de Janeiro - Brazil