Budgeted Costs

A
Andy Quinn 👤 Member for 21 years 1 month
A
Alex Wong 👤 Member for 23 years 5 months

The only think I know to remove non labor budget is reverse status for Actual Finihsed activity.



R U sure it is associated with Start date??

B
Bill McMichael 👤 Member for 21 years 7 months

I cannot think of a scenario that would reset the task’s budget to zero by simply statusing the task with an actual start date.



Here is a place to start.



1. Go to the Project’s Screen , select your project in question , and then go to the Calculations tab (located at the bottom of the screen). This tab contains settings that impact activity and assignment calculations. Perhaps you will notice a setting here that is not configured the way you would like.







Regards,

Bill

Featured Partner

Top Posters

Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts