Just a couple of additional points on the tallys:
myPrimavera uses the tallys to do Return On Investment (ROI) calculations at the project level (NPV, payback period) based on an annual discount rate.
Futhermore these tallys can be handy when integration with (for instance) SAP is established because these systems typically work with monthly budget buckets.
thats very nice of you to share your knowledge with me and other readers. ill use your guide and if i face the problem Ill write it here and hope you give me more guide.
also i wish that everybody understands we are here to learn and share our knowlede with together and planning planet is not a literature website where makes some body be able to show off his dictionary!!!!!!!!!!!!!!
I suggest you look up the word "tally" in a good dictionary, as a sailor we used tallies to see how many people returned, in case the was people lost. In the mines the same system was used.
The chambers dictionaryquotes, "A stick with notches to keep numbers or accounts"
The general idea is to know the status of what is going on, and not a final account.
If you do not understand a word or terminology, try a dictionary or theasaurus as the first help
The spending plan is not related to your schedule in any way, so your spending plan is static top-down estimate in that respect. What would you like/expect it to do?
If you are looking for the data to populate your tally you should just create your schedule, load you resources and costs, and then run a time distributed report on total planned costs by monthly intervals. (youll need to copy/paste the data from the report into the tally for each WBS element where you want to do that exercise)
If this doesnt answer your question please rephrase it because then I dont understand where you get stuck (if that translates).
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
My pleasure Amir,
I hope the answers are useful to you.
Just a couple of additional points on the tallys:
myPrimavera uses the tallys to do Return On Investment (ROI) calculations at the project level (NPV, payback period) based on an annual discount rate.
Futhermore these tallys can be handy when integration with (for instance) SAP is established because these systems typically work with monthly budget buckets.
Best regards,
Niek.
Dear my friend, Niek
thats very nice of you to share your knowledge with me and other readers. ill use your guide and if i face the problem Ill write it here and hope you give me more guide.
also i wish that everybody understands we are here to learn and share our knowlede with together and planning planet is not a literature website where makes some body be able to show off his dictionary!!!!!!!!!!!!!!
ill be glad to hear from you more.
best regards
Amir
I suggest you look up the word "tally" in a good dictionary, as a sailor we used tallies to see how many people returned, in case the was people lost. In the mines the same system was used.
The chambers dictionaryquotes, "A stick with notches to keep numbers or accounts"
The general idea is to know the status of what is going on, and not a final account.
If you do not understand a word or terminology, try a dictionary or theasaurus as the first help
Dear friends
i wrote the wrong sentece!!!!!!!!!!!!
How does spending plan tally work?
regards
Amir
Dear Niek
P3e gives the ability to manage cost from top to down.
and spending plan is not related to schedule, it will be filled base on som prediction or etc
but iam looking for the way to find that ...
how does spending plan work?
as i described in base topic i tried many way to find itaction but unfortunetly i couldnt find it
Amir,
The spending plan is not related to your schedule in any way, so your spending plan is static top-down estimate in that respect. What would you like/expect it to do?
Regards,
Niek.
Amir,
If you are looking for the data to populate your tally you should just create your schedule, load you resources and costs, and then run a time distributed report on total planned costs by monthly intervals. (youll need to copy/paste the data from the report into the tally for each WBS element where you want to do that exercise)
If this doesnt answer your question please rephrase it because then I dont understand where you get stuck (if that translates).
Cheers,
Niek.