Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Procurement Schedule Weights

1 reply [Last post]
Manish Kanojia
User offline. Last seen 8 years 1 day ago. Offline
Joined: 18 Feb 2006
Posts: 3

Hi All,

I am presently working on preparation of overall EPC schedule. I want to add weights to procurement activities like:

. PO Placement

. Vendor doc. approval

. Manufacturing

. Inspection

. Ex Works

 

I can calculate weights as per total equipment cost but how to put this in primavera and then measure procuremrnt progress in order to get the S- curve for plan Vs Actual.

Please suggest how to proceed.

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

use steps and weigth the steps