baseline vs as built

Member for

16 years 3 months

how you do it in p3 is to

openthe project

go to tools

select project utilities

select targets this is where you would select the baseline 

then select forrnat bars 

select modify in the drop donw by where it says structure

for the start point select target 1 early or late start

for the end point select target 1 early or late finish 

upper right make sure that the position of this bar is posiiton 2 or it maybe be drawn on top of your current bar 

Member for

19 years 10 months

Hi Jack

This is how I would do it.

Open the original programme.

Change the durations to the as built dates.

DO NOT SAVE IT.

Create an undelying baseline.

Close the file and DO NOT SAVE It.

Open the file and you have the as built underlying the as planned.

Best regards

Mike Testro