Primavera Project Planner - P3 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2015-06-29 19:40 Permalink how you do it in p3 is how you do it in p3 is to openthe project go to tools select project utilities select targets this is where you would select the baseline then select forrnat bars select modify in the drop donw by where it says structure for the start point select target 1 early or late start for the end point select target 1 early or late finish upper right make sure that the position of this bar is posiiton 2 or it maybe be drawn on top of your current bar Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2015-06-28 08:10 Permalink Hi JackThis is how I would do Hi Jack This is how I would do it. Open the original programme. Change the durations to the as built dates. DO NOT SAVE IT. Create an undelying baseline. Close the file and DO NOT SAVE It. Open the file and you have the as built underlying the as planned. Best regards Mike Testro Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2015-06-29 19:40 Permalink how you do it in p3 is how you do it in p3 is to openthe project go to tools select project utilities select targets this is where you would select the baseline then select forrnat bars select modify in the drop donw by where it says structure for the start point select target 1 early or late start for the end point select target 1 early or late finish upper right make sure that the position of this bar is posiiton 2 or it maybe be drawn on top of your current bar
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2015-06-28 08:10 Permalink Hi JackThis is how I would do Hi Jack This is how I would do it. Open the original programme. Change the durations to the as built dates. DO NOT SAVE IT. Create an undelying baseline. Close the file and DO NOT SAVE It. Open the file and you have the as built underlying the as planned. Best regards Mike Testro
Member for
16 years 3 monthshow you do it in p3 is
how you do it in p3 is to
openthe project
go to tools
select project utilities
select targets this is where you would select the baseline
then select forrnat bars
select modify in the drop donw by where it says structure
for the start point select target 1 early or late start
for the end point select target 1 early or late finish
upper right make sure that the position of this bar is posiiton 2 or it maybe be drawn on top of your current bar
Member for
19 years 10 monthsHi JackThis is how I would do
Hi Jack
This is how I would do it.
Open the original programme.
Change the durations to the as built dates.
DO NOT SAVE IT.
Create an undelying baseline.
Close the file and DO NOT SAVE It.
Open the file and you have the as built underlying the as planned.
Best regards
Mike Testro