Construction Project Planner / Senior Planner, SPI Appleton via Minstrell Recruitmant, Ross Planning contract for SPI Appleton via Minstrell Recruitment – Mersey Gateway As-builts and other analysis in MS Project
Normal 0 false false false EN-US X-NONE X-NONE /* Style Definitions */ table.MsoNormalTable {mso-style-name:"Table Normal"; mso-tstyle-rowband-size:0; mso-tstyle-colband-size:0; mso-style-noshow:yes; mso-style-priority:99; mso-style-qformat:yes; mso-style-parent:""; mso-padding-alt:0cm 5.4pt 0cm 5.4pt; mso-para-margin:0cm; mso-para-margin-bottom:.0001pt; mso-pagination:widow-orphan; font-size:11.0pt; font-family:"Calibri","sans-serif"; mso-ascii-font-family:Calibri; mso-ascii-theme-font:minor-latin; mso-fareast-font-family:"Times New Roman"; mso-fareast-theme-font:minor-fareast; mso-hansi-font-family:Calibri; mso-hansi-theme-font:minor-latin; mso-bidi-font-family:"Times New Roman"; mso-bidi-theme-font:minor-bidi;}
Further work requested on delay programme for the Mersey Gateway river crossing, construction of trestle bridge and cofferdams, as it nears completion, the original programme being developed by me a year previously, then the programme was taken over by SPI-A. The scope of work is updating SPI's construction programme to substantiate weather delays working in MS Project. Liaise with the Contracts Manager in Bolton but generally working from home for a robust substantiation of all delays, prolongation and disruption to the critical path, may also be required for a meeting or two in Bolton or with MCCJV (Mersey Civil Constructors Joint Venture). No work requested since Nov 2015.