Is this possible to fix the manhours for unit of work as the permanent? (P3)

2 replies [Last post]
Oxana Chepelyova
User offline. Last seen 13 years 3 weeks ago. Offline
Joined: 23 Jan 2008
Posts: 3

Dear all,

I need your assistance.

 

My boss is asking me about the fixing of the manhours for unit of work. I do not know how I can do this.

Thank you.

 

Replies

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Oxana

It seems that your boss is asking about production rates.

ie how many blocks can a blockwork gang lay in one hour.

The answer has to come from the production rates used in the pricing build up so the first call will be to your estimating department.

If you are tempted to look at the PP rates and norms section then do so with care as the data may not be applicable to your own projects.

Best regards

Mike Testro

Shareef Abdul Azeez
User offline. Last seen 3 years 21 weeks ago. Offline
Joined: 19 Sep 2005
Posts: 183

 

Hi

Check "Freeze -Units/time period" in the options tab