Irregular Results in P3

7 replies [Last post]
Jhorbam Baena Orozco
User offline. Last seen 3 years 10 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None

Hi everyone, i have the following problem with P3...in my excel control sheet the mecanica group show a execute of 4.68% and in P3 after the schedule process show 44%, having the activities the same values in both excel and P3.

The formulas in excel where revisated and are good, but in P3 when i was checking one by one the activities of the mecanica group and summarizing each subgroup i found that P3 make the follow...in some subgroups having the activities 0% in the percent Complete column...P3 show when i summarize the group, a value in the percent comple cell of the sumarized group, likewise if i do a change adding some value to one activitie of the mecanica group and summarize the group.

The files (Control sheet in excel and the Primavera Project files), was uploaded into mediafire server.

The link to download the file is [URL=http://www.4shared.com/file/65kV7Hlw/Planning_Planet.html]Planning Planet.rar[/URL] or http://www.4shared.com/file/65kV7Hlw/Planning_Planet.html



I wait for comments to found a solution to my problem....thanks...sorry by my english.

Replies

Justin James
User offline. Last seen 5 years 50 weeks ago. Offline
Joined: 19 Aug 2009
Posts: 32
Groups: GPC Qatar, TILOS

Hai Eugene , 

Can u post your primavera file here, we can sort out your problem.

Regards

Justin

vimal mohan
User offline. Last seen 12 years 16 weeks ago. Offline
Joined: 5 Jul 2009
Posts: 5

Its really strange that an activity with AS and AF having RD. As far i knew, p3 have one problem that it calculates the date with respect to the per cent completed, not with quantity remaining. For changing any calculation method we have to go to Autocost rules and change it. But i have never come across such problem.

Eugene K
User offline. Last seen 13 years 32 weeks ago. Offline
Joined: 18 Oct 2006
Posts: 47
Groups: GPC Malaysia

I have been using P3 for more than 10yrs and finally a got a result which is impossible.

An activity with AS and AF, but PCT = 80% and RD = 9 !!!!

F9 does not correct the problem. However, if i type any value in PCT (not necessarily 100), P3 will correctly re-calc the PCT as 100% and and RD=0.

The strange thing is I do n ot how the activity can be 80% with RD, and has AS and AF in the first place!

 

Thought it could be an IMPORT malfunction, but when I tried to replicate the problem using the 2 screnarios below, P3 still did not produce that irregularity results.

  1. Preset activity as 100% with AS and AF. Then IMPORT only PCT=80. P3 cleverly ignore the import values. Activity retained as 100% with AS and AF.
  2. Preset activity as 80% with only AS, no AF. Then IMPORT only AF=04JUN. P3 correctly set activity as 100%

Anyone come across this irregularity before?

 

Thanks.

Jhorbam Baena Orozco
User offline. Last seen 3 years 10 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None

Thanks to all ...thanks a lot....good explanations...thank you

Anoon Iimos
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422

in P3, go to Tools, Options, Summarization; from there you can choose your weighting factor;

don't be surprised if you found different results after calculations, again, it is because of consistency

Haitham Khaireldin
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 36
Groups: None

As Justin mentioned, what you're getting as percent complete from the summarized group is based on duration.

When i made a resource loading report based on cost from your Primavera file i fould out that the percent complete for "ESPECIALIDAD MECANICA" up to the 28th of April 2011 is 4.78% and not 4.68%

Justin James
User offline. Last seen 5 years 50 weeks ago. Offline
Joined: 19 Aug 2009
Posts: 32
Groups: GPC Qatar, TILOS

Hai Mr.Jhorbam Baena,

I reviewd your schedule and XL workings , what i found is that your XL waitage is based on COST , but in P3 will calculated the progress based on DURATION , so as per cost your progress is 4.68 % , but according to duration it is 44 % in P3,

 

Regards