Hi everyone, i have the following problem with P3...in my excel control sheet the mecanica group show a execute of 4.68% and in P3 after the schedule process show 44%, having the activities the same values in both excel and P3.
The formulas in excel where revisated and are good, but in P3 when i was checking one by one the activities of the mecanica group and summarizing each subgroup i found that P3 make the follow...in some subgroups having the activities 0% in the percent Complete column...P3 show when i summarize the group, a value in the percent comple cell of the sumarized group, likewise if i do a change adding some value to one activitie of the mecanica group and summarize the group.
The files (Control sheet in excel and the Primavera Project files), was uploaded into mediafire server.
The link to download the file is [URL=http://www.4shared.com/file/65kV7Hlw/Planning_Planet.html]Planning Planet.rar[/URL] or http://www.4shared.com/file/65kV7Hlw/Planning_Planet.html [1]
I wait for comments to found a solution to my problem....thanks...sorry by my english.