level 3 programme

2 replies [Last post]
ronron martinez
User offline. Last seen 7 years 27 weeks ago. Offline
Joined: 19 Nov 2009
Posts: 41

Hi, All

i am new in planning, currently we just got a small project doing EPC, my Project manager ask me to prepare level 3 programme/schedules. kindly please guide me the detail to be input into the schedules.

Please PM me thanks

Regard's

Ron

Replies

Evaristus Ujam
User offline. Last seen 11 years 51 weeks ago. Offline

Hi Ron,

You can always create a level 3 programme/schedule if you really know what you are doing. Since you are in oil and gas we really can flow as I am going to drive home all am going to say to you under this forum. The WBS is your first port of call. Your EPC Project tittle is your level 0. Under EPC  you have 1.0 Engineering, 2.0 procurement & 3.0  Construction at level 1.

Engineering can be broken down into level 2 as follows:

1.1 process Design 1.2 Mech 1.3 E &I  1.4 Civil/Structural.

1.1 Process can further be broken down to level 3 as follows:

1.1.1  "Valves,gauges    & Pressure control Devices" 

1.1.2       P&ID's 

1.1.3      vents & Bypass Systems 

 

Mechanical  can also be broken down to level 3 as follows:

1.2.1  Plot plan

1.2.2 Pipe Rack

1.2.3 Compressors

Ron, what I have done for Process & Mech, I expect you to do for E&I and civil structural.

When you are done with Engineering, then get to procurement & list out the equipment you want to procure section by section. Take for instance Auxilliary equipment might be your level 2. Level 3 will comprise everything you need to procure under auxilliary equipment. e.g inlet separator, scrubber, PLC panels etc. When you are done with procurement, proceed to construction and develop your WBS to level 3 schedule. Please if you need more clarifications do not hesitate to keep in touch so you can be properly guided.                                                                                           

Regards                                                                                                                                                       

Ujam

Mike Testro
User offline. Last seen 18 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ronron

It is not a good idea to create a Level 3 programme without a detailed Level 4 programme underneath it.

So create a Level 4 task based programme and summarise the tasks to Level 3 and you will have an accurate and realistic programme.

It does not take long to do a fully detailed level 4 programme if there is a lot of repetition where you can copy paste the tasks and link up.

Best regards

Mike Testro