P3 data saving before new updating

2 replies [Last post]
Kannan CP
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi,

What method to follow to save the data in the schedule(for eg: cost, budgeted quantities etc) while next updating of the schedule.

Thanks in advance.

Kannan

Replies

Kannan CP
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Ronald,

Thanks a lot

Kannan

Ronald Winter
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Kannan,

 

You should never modify your schedule once you published it.  Instead, you should make a complete copy of the schedule (under Tools / Project Utilities / Copy) and then update the copy.  Leave the old schedule untouched so that you can use it as a baseline.  Good luck!