Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to Set up cut-off date in P3

6 replies [Last post]
Angel Cruz
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 16 May 2010
Posts: 16
In the tabular reports resource loading. For example P3 calculate output with MONDAY cut-off on weekly base. How to set-up cut-off date to FRIDAY?

Replies

Angel Cruz
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 16 May 2010
Posts: 16
Tnx to all i got it. This forum is amazing...
Anbin Ponnith
User offline. Last seen 8 years 36 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Dear Angel Cruz,
I find another Option also which is very easy
Data->Calender->Click Global Calender->Standard->Week start on -> Change to Saturday
I tried it Just Now it Work
Regards
Anbin
Anbin Ponnith
User offline. Last seen 8 years 36 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Dear Alexandre,

I tried your solution but could not find any option to change the 1st day of the week to Saturday..

Could you please expain me in detail.


With Thanks & Regards,

Anbin Ponnith
Anbin Ponnith
User offline. Last seen 8 years 36 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Hai Angel Cruz
U try the Following Option
1.First Create a new Project(ABC)in that give Week start on Saturday
2.Open your Current Project Select all Activities
3.Click Tools->Fragnet->Store Fragnet->Type Id->Type Title
4.Open the New Project (ABC)Transfer all the Dictonary Like
a.Activity code
b.Resource
c.WBS
5.Tools ->Fragnet->Restore Fragnet->Select Correct ID u Typed Before
6.Select Rename Duplicate Only -> OK
7.Now u Can see the New Project Similar to the Current Project
8.Now U can Try Tabular Report
I Hope it works
Regards
Anbin