Task Stand-by

3 replies [Last post]
harzelli bouasria
User offline. Last seen 4 years 50 weeks ago. Offline
Joined: 15 Oct 2008
Posts: 42
Hi all

how we can put 2 stand-by on the same task (dates)

Replies

Safak Vural
User offline. Last seen 4 years 15 weeks ago. Offline
Joined: 12 May 2008
Posts: 117
Dear planners,

You cannot in P3. You shall divide the activity. If the suspend is about dates only, you can create a specific calendar that the suspended days are not working.

But as a schedule and CPM point of view you should divide the activity.

Regards,

Safak VURAL
harzelli bouasria
User offline. Last seen 4 years 50 weeks ago. Offline
Joined: 15 Oct 2008
Posts: 42
hi shahul
it’s mean suspend and resume date, how we can put 2 on the same task in P3
Shah. HB
User offline. Last seen 41 weeks 6 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi Harzelli

What does stand by mean? and With reference to which task are you referring