Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Bars and Baselines in P6

1 reply [Last post]
James Braghini
User offline. Last seen 14 years 19 weeks ago. Offline
Joined: 28 Apr 2008
Posts: 51
Groups: None
How can I get the bars for both Primary and Secondary Baselines to come up on Gant Chart? Also, I was wanting to have the Predessor be on the Primary and the Successot to should on the Secondary.

Can someone give a quick lesson on this?

Thanks,
James Braghini

Replies

Arnold Puy
User offline. Last seen 10 years 3 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi James,

You can do this by Formatting your Bars. Before doing this make sure that you have assigned both for primary & secondary baseline.

Afterwards, Go to View -> Bars -> mark the box next to "Primary & Secondary" under the bar style tab you change the shape, color, pattern & row. Under the bar labels tab, select the "primary" & select add underneath & select label as predecessor. Do the same way with the secondary.

HTH.