Importing % Progress from Old Schedule to New Schedule

2 replies [Last post]
Jun Gallardo
User offline. Last seen 8 years 42 weeks ago. Offline
Joined: 12 Apr 2008
Posts: 22
In P3, can anyone teach me how to import % progress on all activities of my old schedule to my new schedule. Regards.

Replies

Jun Gallardo
User offline. Last seen 8 years 42 weeks ago. Offline
Joined: 12 Apr 2008
Posts: 22
Brennan,

It worked. Thank you.


Jun
Brennan Westworth
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
two ways i can think of are to use export import or target update

export import

1. back up both schedules

2. open the old schedule and to go tools, project utilities, export

3. add a new specification

4. in the content tab include only activity ID and % complete (you might also want remaining duration)

5. in the format tab I usually use .DBF you can keep the file name C:\P3WIN\P3OUT\P3 if its just a 1 off.

6. leave selection blank for all activities or set up a filter for the activities you want and click RUN

7. open the new schedule

8. go to tools, project utilities, import

9. add a new specification

10. enter the path to your file (C:\P3WIN\P3OUT\P3.DBF)

11. cross your fingers and click RUN


or u could use Target update

1. back up both schedules

2. Open the old schedule

3. go to tools, project utilities, targets and set the new schedule as a target.

4. select the new schedule and click the update button. You may need to try this a couple of times with different options selected in the update target dialogue box



HTH