Planning using Meters - P6 - NATM Tunnel

10 replies [Last post]
Shane Stanford
User offline. Last seen 16 years 3 weeks ago. Offline
Joined: 1 Nov 2008
Posts: 7
Groups: None
Hi guys,

Im new to P6 and planning, I am working on a Tunnel job in the UK and would like to show meterage on P6, for example -
Week 1,2,3 and 4 - 42 meters of tunneling is predicted each week, but week 5 only 36m because of bad ground expected. Is there a way I can manage progress like this and show it on P6?

The only way I can seem to manage this is by using excel spreadsheets, but id rather keep it on one software program.

Thanks

Replies

A D
User offline. Last seen 4 years 3 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
If u r not getting spreadsheet in ur preview, then go to page set up --> Options --> Check on SPREADSHEET box.

KHALLAS!!!

:-)
Shane Stanford
User offline. Last seen 16 years 3 weeks ago. Offline
Joined: 1 Nov 2008
Posts: 7
Groups: None
Yep, thank you Dieter, Raviraj and Vladimir.

All sorted now... Now all I have to do is print the resource usage chart and the gantt on the same page :-)
Dieter Wambach
User offline. Last seen 7 years 32 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Shane
I don’t really understand your item.
P6 has the resource type "material".
1. Define required unit of measure - if not yet done:
Admin --> Admin Categories --> Units of Measure --> Add ...
2. Define Resource of type Material - under Details.
3. Assign this resource to those activities you’ll need.
4. To have an overview and the results of your planning: View--> Show on bottom --> either Resource Usage Spread or Resource Usage Histogram. One restriction: you can just show resources with the same unit of measure in the histogram.
Was this your question?
Regards
Dieter
Shane Stanford
User offline. Last seen 16 years 3 weeks ago. Offline
Joined: 1 Nov 2008
Posts: 7
Groups: None
All I really need it to do is display how many meters we are are expecting to do each week, and be able to put in actuals throughout the project. The resource schedule looks like the ideal layout, but it edits when scheduled.

Thanks for your help so far too.

Shane
Actually there is a need to link a lot of data with these meters (physical quantities of work - physical volumes) - material requirements per each meter, cost per meter, resource productivities in meters per hour, etc. Unfortunately Primavera do not plan physical quantities of work to be done, if you need it try to find some other software. Workarounds do not help.
A D
User offline. Last seen 4 years 3 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Shane,

Check ur resource levelling options. (Go to Tools --> Level Resources)

Uncheck theses three options:
- Automatically level resources when scheduling, AND
- Preserve scheduled early and late dates
- Level all resources

Cheers,

Rav
Shane Stanford
User offline. Last seen 16 years 3 weeks ago. Offline
Joined: 1 Nov 2008
Posts: 7
Groups: None
Thanks Raviraj,

I think I got it now - they seem to be a little erratic though, as I would like to click on week one and assign 42 meters, then week two and assign 36 meters and so on. but when I change datesand reschedule, the usage changes.
A D
User offline. Last seen 4 years 3 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Add a resource and then add budgeted quantity. U can check Resource usage spreadsheet.

Shane Stanford
User offline. Last seen 16 years 3 weeks ago. Offline
Joined: 1 Nov 2008
Posts: 7
Groups: None
Thanks for that... Anyone i know how to do it?
Anoon Iimos
User offline. Last seen 2 years 46 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Yes