how to monitor cost in hammock activity???

2 replies [Last post]
nizam shukkur
User offline. Last seen 15 years 46 weeks ago. Offline
Joined: 10 Aug 2005
Posts: 4
Groups: None
Help me. I have listed 14 hammock activities in the schedule and have loaded the cost as a resource.
I have updated the schedule.
When i view the tabular report for the cost it does not show the actual cost completed so far but instead distributes the total cost of the project from the data date till the end of the project.
Can someone help me in finding the actual cost completed using this hammock activities

Replies

nizam shukkur
User offline. Last seen 15 years 46 weeks ago. Offline
Joined: 10 Aug 2005
Posts: 4
Groups: None
Thanks for that Arnold
Arnold Puy
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Nizam,

Hammock activities does not update automatically. Even though you have % complete in it. You have to update manually.

HTH.

Arnold