Deleting constraints

6 replies [Last post]
moutaz aldeib
User offline. Last seen 2 years 39 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Dear Planners,

How to delete early constraints for many activities in the project by using Global Change?

Regards,

Moutaz

Replies

moutaz aldeib
User offline. Last seen 2 years 39 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Dear Arnold & Alexandre,

Thanks a lot, it is wroking now.

Regards,

Moutaz
Arnold Puy
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Alexandre,

Thanks, but I forgot to insert the space between quotes. I didn’t notice.

Sorry Moutaz. Alex is right.

Arnold
Arnold Puy
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Moutaz,

You are using P3, right? Then it is working with me.

Regards,

Arnold
moutaz aldeib
User offline. Last seen 2 years 39 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Dear Arnold,

It is invalid statement

Regards,

Moutaz
Arnold Puy
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hello Moutaz,

To delete Early Constraints, use this parameters:

Then: SNE EQ ""

Regards,

Arnold