Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

SPI & CPI

3 replies [Last post]
Rejo Poothokaran
User offline. Last seen 13 years 16 weeks ago. Offline
Joined: 19 Jul 2008
Posts: 8
Hi All,

Could anyone tell me, what is SPI & CPI ?

Replies

Rejo Poothokaran
User offline. Last seen 13 years 16 weeks ago. Offline
Joined: 19 Jul 2008
Posts: 8
Thanks to all
Arnold Puy
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi,

SCHEDULE PERFORMANCE INDEX (SPI) – the ratio of work performed (earned value or BCWP) to work scheduled (planned value or BCWS).

COST PERFORMANCE INDEX / INDICATOR (CPI) – the ratio of earned value to actual costs (CPI = BCWP/ACWP). A value greater than 1 indicates that costs are running under budget. A value less than 1 indicates that costs are running over budget. Often used to predict magnitude of a possible cost overrun by dividing it into the original cost estimate (original cost estimate / CPI = projected cost at completion).
Shaneouz Kallal
User offline. Last seen 13 years 19 weeks ago. Offline
Joined: 15 Feb 2008
Posts: 6
Hi,
SPI = Schedule performance index
CPI = Cost performance index
Please see details P3 manual or help.

Shaneouz