Hammock Activity

4 replies [Last post]
Izam Zakaria
User offline. Last seen 7 years 42 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
I’m facing problem as subjected above
As known hammock can calculate progress based on difference between the original and remaining duration divided by original duration....but what happen to me, the percentage column shown zero... wise gents...please advise me....

Replies

Izam Zakaria
User offline. Last seen 7 years 42 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
but remember...this what the real function of hammock "An aggregate or summary activity. All related activities are tied as one summary activity and reported at the summary level" and if we doesn’t use it...what purposely it is?
Johny Kesserwany
User offline. Last seen 7 years 36 weeks ago. Offline
Joined: 18 Sep 2007
Posts: 118


I totally agree with Andy don’t use hammocks!

Jk
Ramil Hajizalov
User offline. Last seen 16 years 20 weeks ago. Offline
Joined: 4 Oct 2007
Posts: 3
Groups: None
HI Izam,

you can try this:
TOOLS>OPTIONS>AUTOCOST RULES> adn click on "LINK REMAINING DURATION AND SCHEDULE PERCENT COMPLETE"
then reschedul your schedule
it should automaticali counts the %

Ramil
Andy Petkus
User offline. Last seen 12 years 17 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 44
Groups: None
Hi Izam,

I’m assuming you are working on a petro-chem project?

If you are, why are you using hammocks? I’m also in the same game and have advocated that the use of hammocks be banned altogether as projects of this nature demands programme and logic flexibility which hammocking severely restricts.

For example, on a project I was on, the contractor insisted on using hammocks. I got their monthly progress update which showed the end date being pushed out. It took me 2 days to find out why. What happened was that the planner put in a really stupid logic string inside a hammock - a SF relationship with a forced negative float - crazy!

Hammocks are of any value in a conveyor belt or assembly line situation where lower level tasks are repetitive and can be summarised.

My advise to you is - get rid of hammocks entirely in your programme!

You problem is typical of trying to run a programme with hammocks. For summarising tasks, why not just use your activity codes or WBS.

Good luck