Inter-Project Relationship Manager

10 replies [Last post]
Ife Olyke
User offline. Last seen 10 years 9 weeks ago. Offline
Joined: 6 Feb 2007
Posts: 147
Please how can i set up interproject relationship manager on my project? i understand it’s an application that comes with P3 installation...Thanks

Replies

Ife Olyke
User offline. Last seen 10 years 9 weeks ago. Offline
Joined: 6 Feb 2007
Posts: 147
Who knows how i can get my interproject relationship manager to work in a multi-user environment.. It appears to work only in a stand-alone workstation.. Any ideas? Thanks..

Ifeanyi

DATTATREYA PADHARTHI
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 18 Apr 2003
Posts: 90
Futher to the earlier post on Interproject relationships, we are scheduling & levelling resources thru the InterProj quite well & getting desired outputs.
Only hassle is to define relationships one by one. Wonder if someone has developed a utility to automate the relationships.

Cheers

Dattatreya
DATTATREYA PADHARTHI
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 18 Apr 2003
Posts: 90
We have a situation where two projects are run concurrently on stand alone P3 with engineering resources more or less distinct, but the Job Card members are shared.
Initially we allocated resource limits as 50% each for the members which is tedious , time consuming & in accurate.
Now We are going for a third distinct plan for for the Job Card team with the Job Card resources, using Interproject relationships for getting the Drawings/Document completion dates & then levelling the Job Card resource in the Third Plan. There is a difference of data date by 1 day (Saturday/Sunday) which does not make any difference.
& scheduling in sequential order to get an accurate scenario.

But yes, we are waiting for P6 to be "Officially" purchased & used.

Cheers
Dattatreya
Frank Borcherdt
User offline. Last seen 7 years 35 weeks ago. Offline
Joined: 3 May 2001
Posts: 88
Groups: None
The interproject relationships are stored in a seperate file and updated each time according to the advanced scheduling options. They act as a constraint on the activity in the current schedule. This is also option based.

If your data dates are different then either the activity in the current schedule has started (therefore constraint gets overridden) or not started in which case the inter-project constraint is applied. The constraint date is calculated based on the different data date and progress on the predecessors in the other project group.

Frank
Ife Olyke
User offline. Last seen 10 years 9 weeks ago. Offline
Joined: 6 Feb 2007
Posts: 147
Frank,

Thanks for your comment. Following your example, what impact would it have if the data date for the design program is different from that for the possession program? for e.g. data date for design schedule is monday, and data date for possession schedule is sunday. will impact the possesion schedule? Thanks.

Ifeanyi
Frank Borcherdt
User offline. Last seen 7 years 35 weeks ago. Offline
Joined: 3 May 2001
Posts: 88
Groups: None
A word of caution if you use Interproject relationships.

You must attempt to keep all interproject relationships going the same direction otherwise you will need to reschedule the Project Groups (the relationships are between activities in Project Groups) in sequence to get the correct result.

IMHO the ONLY valid use for Interproject Relationships is when you have the need to have different planning units ie. the design and leadup to a rail possession occurs in days and the execution of the possession is in hours. The interproject relationships in this example then tends to be in the same direction ie from the design program to the possession.

HTH

Frank Borcherdt
Ife Olyke
User offline. Last seen 10 years 9 weeks ago. Offline
Joined: 6 Feb 2007
Posts: 147
Thanks a lot Andrew. I can access it now.
Andrew Podolny
User offline. Last seen 1 year 5 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 130
the password is
intrproj
Ife Olyke
User offline. Last seen 10 years 9 weeks ago. Offline
Joined: 6 Feb 2007
Posts: 147
Thanks Steven.

found it, but its password protected.
Steven Oliver
User offline. Last seen 11 years 38 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Should be installed in the Primavera Programme Group.

Look for a filename INTRPROJ.EXE