Inter-project links

3 replies [Last post]
Y Malik
User offline. Last seen 5 years 51 weeks ago. Offline
Joined: 27 Nov 2010
Posts: 5
Groups: None

Hello folks,

This in regards to my effort to carry a summary level schedule (about ~ 250 lines), out of 10000 line itmes schedule, to provide the management,  overall high-level view of the project. The big part of the 10000 line items is EPCM schedule, which gets updated monthly. The way I created it, I used summary LOE activities in summary schedule and linked ss and ff with 10000 lne item schedule. However, when I update it on monthly basis and re-schedule, I start getting circular relationship issue and I can not update the ISS file. I was wondering help on 2 things:

What might be the issue that seems to causing the circular relationship & 

Is there a better way to manage standalone integrated summary schedule 

Many thanks in advance for your help.

Younus

Replies

Rafael Davila
User offline. Last seen 1 day 9 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5234

It will not work when summary bars are defined by more than one activity code. 

As things change the relative position of the activities may change as well as the summary bars and their overlap.  In order to get the correct summary bars defined by multiple activity codes you cannot exclude any activity from any of the summary bar with matching activity code.

Portfolio_Summary_Bars

Santosh Bhat
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

David Kelly's suggestion will work, do the following

1) Create a new Activity Code called "Summary" (or whatever you choose)

2) Use the Hierarchical structure of activity codes to build this "Summary" activity code into a quasi-WBS structure

3) Assign all 10,000 activities to their corresponding "Summary" activity code - if they don't belong to any, you will also need to create a filter to exclude these activities

4) Group by the "Summary" Activity code and display Group Summary bars only.

David Kelly
User offline. Last seen 2 years 7 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Yes. Use Activity codes instead of LoE activities.