Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Level-3 and Level-4 Schedules

4 replies [Last post]
Rey Basadre
User offline. Last seen 16 years 39 weeks ago. Offline
Joined: 5 Mar 2006
Posts: 24
Every contractor, every planner/scheduler, has his own idea or version of structuring level-3 & level-4 schedules. One contractor may say his is a level-4 but I may call it level-3, a Contract may specify a level-3 schedule but the breakdown of detail of activities demanded by the owner’s Project Management Team is as good as level-4. Contractors or PMTs may even direct its planners/schedulers to create a hybrid level 3.5 Schedule. Now, isn’t that something?

It is long overdue that scheduling levels be STANDARDIZED, or a least a guiding structure & requirements be authored & presented, something in the line of how detailed the breakdown of activities in the schedule should be, the maximum duration of each activity, resource load, etc.

Your opinions please...

Replies

Ahmed Syed
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 27 Mar 2007
Posts: 21
Groups: None
Hi All
CSI MasterFormat 2004 would be your answer for standarizing activities. It covers pretty much everything.
regards
Bijaya Bajracharya
User offline. Last seen 8 years 43 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
I don’t think there can be industry standard on such things. All the projects are different. Even within a project, a structure which is perfect for one Manager may not be good for the other. Thus this level does not mean anything. Start from absolute activites ( you may call it level 1). For your and others clarity and ease, group and subgroup them in whatever way until your requirements are met.

If someone comes to you asking for Level 3 or whatever level programme, ask him what he means.
Rey Basadre
User offline. Last seen 16 years 39 weeks ago. Offline
Joined: 5 Mar 2006
Posts: 24
Hi Hannes,

Interesting opinion, thanks.

I am posing a construction working-schedule assertion, one that will serve not only management or contracts people but a realistic schedule that every discipline manager, superintendent, supervisor, foreman, and leadmen will observe and implement in actual work.

I hope to read more opinion from others.

Cheers,

Rey
Hannes de Bruyne
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 25 Jul 2005
Posts: 154
Groups: None
Hello Rey

this is not a question of standard, it is a question of wording. Only the level 1 - schedule is clearly specified. Out of this description people started to make expressions like level 2 and so on. It is a bad habbit to use level description higher than "1" and people using this description mostly do not know what they are talking about.

Hannes