Target/Baseline Critical Activities VS Present status

11 replies [Last post]
Pranab Kumar Deb
User offline. Last seen 3 years 32 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Dear All,
I have a program statused today , i want to see the status of the target critical Path vs the present state of the activties. Can anyone guide me how i can make a layout of this.
regards
deb

Replies

Amreshwar Shukla
User offline. Last seen 1 year 44 weeks ago. Offline
Joined: 6 May 2003
Posts: 53
Groups: None
Will you please send a copy of same to me ??? My email is shukla@myrealbox.com

Thanks in advance.

A.S.SHUKLA
Pranab Kumar Deb
User offline. Last seen 3 years 32 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Actually i got those Excel workbooks from Rodel so i called it like that , its just two work books in excel named activity and project , with which u can make global changes to a project.
regards
deb
Anoon Iimos
User offline. Last seen 3 years 3 days ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Deb,

it seems that you like Rodel more than me, yes, what’s Rodel’s excel utilities anyway? does it have target/baseline critical activities also?
Amreshwar Shukla
User offline. Last seen 1 year 44 weeks ago. Offline
Joined: 6 May 2003
Posts: 53
Groups: None
What is Rodels Excel utilities ??
Pranab Kumar Deb
User offline. Last seen 3 years 32 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
thanks Anoon Iimos tried that but had a shortfall for the presentation
regards
deb
Pranab Kumar Deb
User offline. Last seen 3 years 32 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291

Thanks steven was trying the way u asked actually if i swap the programs the problem is i cannot show the percent complete of the activities in the layout , this presentation i want to make to reinforce my EOT claim , so i wanted it to be self explanatory , actually i wanted to show the knocking effect the 3 times increased volume of excavation and delay in the issuing of shop drawings for the roof structural steel works had on the project both this activities were in the critial path to start with , but as the project progressed the critical path shifted so i wanted to show the impact on the actual baseline critical path.
Thanks again bijaya the solution offered by you was just marvellous , just to avoid the time consuming practice of taking print and then updating the activity code to current schedule i did it with Rodels Excel utilities its just superb.
regards
deb
Anoon Iimos
User offline. Last seen 3 years 3 days ago. Offline
Joined: 22 Sep 2006
Posts: 1422
before I give up, I’d like to try Steven O’s solution!
Bijaya Bajracharya
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
There is no easy filter to sort out critical activities of the target programme.

This solution may help:

Open your target programme and filter for critical activities (whatever way you have difined it - Longest or with float less some certain value). Make a new activity code to show that they are critical activities.

Make a print out (can make it easy).

Now open your current programme and give the same new activity codes to those activities.

Since target programme is a one time operations, even if it takes a long time to create your first current programme, you have now original critical path information in your current programme forever.
Steven Oliver
User offline. Last seen 12 years 8 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Make your current project a baseline of your target project
Pranab Kumar Deb
User offline. Last seen 3 years 32 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Dear Mr. Anoon,
Actually i could not make u understand my problem , i have the Target Project Now in a layout i want to see only the critical activities of my target project and how the critical path was affftected due to some external affects on the project , i.e i want to have a layout of only the Target critical activities and the status of the activities at present.
regards
deb
Anoon Iimos
User offline. Last seen 3 years 3 days ago. Offline
Joined: 22 Sep 2006
Posts: 1422
open your Target Project at the same time with your Current Project, and compare (make sure they got the same data date). or just show your target in your current schedule, and choose criticalities to be shown in the Target Project.