Resources on Summary Bars

2 replies [Last post]
david milburn
User offline. Last seen 16 years 43 weeks ago. Offline
Joined: 6 Mar 2003
Posts: 4
Groups: None
I’m new to P3 so please go gentle !
Is it possible to assign resources to summary bars?
Id like to be able to allocate some staff resources to the overall project rather than specific activities. Is this possible, i cant find a way to do it.

thanks in advance

Replies

Mohamed Ibrahim
User offline. Last seen 12 years 27 weeks ago. Offline
Joined: 18 Nov 2005
Posts: 11
Groups: None
David,

The easy way is to insert an activity and change the type to WBS instead of task and then schedule, there is no need for any links and this will be similar to the summary bar and you can assign resources to this activity with your lag and duration for each resource as normal.


Kind Regards
Mohamed
Gün Göksu
User offline. Last seen 2 years 30 weeks ago. Offline
Joined: 31 Mar 2005
Posts: 123
try and use a hammock activity. start-start to first activity in schedule, finish-finish to last activity in schedule. activity type: hammock. it is good practice to link the start and ends to milestones. Gün.