moutaz aldeib
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Dear All,

Can anybody tell me what is the benefit of using PERT view in program contains more than 1000 activities linked?

Thanks in advance

Replies

John Raper
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 17 May 2004
Posts: 44
Groups: None
Moutaz

It is easy, but you need to make use of the tools available in P3.
Try filtering for critical activities (TF<1) to reduce the number of activities in view.
Use the ’Trace Logic’ window in Pert View. This shows a small window at the bottom of the screen with the selected activity in the centre. You can click on the activities either side to trace through the logic.

I agree 1000+ activities is hard to see on the screen!

Good luck
John
moutaz aldeib
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Thanks every body but I think it is not so easy to use PERT in CPM analysis.

Thanks alot.

Moutaz
Alex Wong
User offline. Last seen 11 years 48 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Logic and CPM analysis is easier in PERT chart

MK TSE
User offline. Last seen 4 years 38 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
I filter the concern activities on PERT to check the relationship