How to change "Week starts on" on existing schedule?

2 replies [Last post]
Jaime Linchangco
User offline. Last seen 16 years 8 weeks ago. Offline
Joined: 16 Jul 2001
Posts: 29
Groups: None
Good Day Fellow Planners!

I have this problem regarding weekly resource loading reporting. Our cut-off date for reporting is every friday but the resource laoding report begins every Monday due to the fact that when our previous Planner specified that week starts on Monday during the time he made the new schedule file.

My question is, is it still possible to change the "Week Starts on" from Monday to Saturday?

I would highly appreciate if anyone there experienced this and find the solution.

Thank you in advance!

Jaime Linchangco

Replies

Jaime Linchangco
User offline. Last seen 16 years 8 weeks ago. Offline
Joined: 16 Jul 2001
Posts: 29
Groups: None
ICQ,

Thanks Mate! Problem solved and i finally made the report better.

Regards,

Jaime
IC Quiamco
User offline. Last seen 14 years 13 weeks ago. Offline
Joined: 20 Dec 2002
Posts: 48
Jaime,

Just adjust your global calendar (week start on).

Data/calendar/global calendar/standard/week start on


Hope this help

ICQ