resource curves

S
saif ansari 👤 Member for 20 years 2 months
R
Rual Brits 👤 Member for 21 years 6 months

Anyone know how to do this with Suretrack ? I use P3 and cant get the same report from Suretrack (Never used before)

R
Rey Basadre 👤 Member for 20 years 3 months

Saif,



Resource curve is a representative S-curve of quantity. Say, a curve of total concrete volume required over the time period or duration of the schedule. Corollary to that, your schedule must be resource loaded before you can generate the curve.



Example:

With several "concreting" activities spread across your schedule, the curve can be generated either by:



1. Directly using "Tools\Graphic Report\Resource and Cost" menu, or,



2. Work in Excel/Lotus spreadsheet using "Tools\Tabular Reports\Resource\Loading" menu (generate in CSV format).



Use the timescale (monthly/weekly/daily) in choosing which one suit your requirement.



From this S-curve, the next period (forecast) quantity required is determined.



I hope this will help.



Rey B.

Forum Sponsor

Top Posters

Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts