Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

As-Built Activities in Critical Path

1 reply [Last post]
Kashyap Mothali
User offline. Last seen 13 years 3 weeks ago. Offline
Joined: 4 Apr 2005
Posts: 23
Groups: None
Why is it that sometimes as-built activities appear on the Critical Path/ Longest Path?

Also, when they do, why don’t they back up all the way to the begining of the Critical Path/Longest Path?

I normally filter these out, but i am curious as to why this happens.

Pleae advice. Thanks,

KM

Replies

Ronald Winter
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Any completed activity that is logically included in the current longest path is reported as being on the longest path. To not do so would leave a gap in the longest path. P3 identified this activity while tracing the controlling predecessor back from the last activity in the schedule. P3 stops tracing the controlling predecessors when it reached the last unfinished activity in this chain.

This technique does not allow for the identification of a longest path for completed activities with an internal scheduled start ‘before the data date’ otherwise. Good question!