Autocost Rules

2 replies [Last post]
Chris Murray
User offline. Last seen 18 years 20 weeks ago. Offline
Joined: 10 Mar 2004
Posts: 12
Groups: None
All,

For some reason I can’t get this to work.

Quite simply all I want to do is to increase the duration of an activity then the budgeted quantity of the resouce increase accordingly.

E.g.
Duration 40d
Resource 40days work
Change:
Duration 42d
Reource to increase 42 days work i.e. Unit per day to stay at 1!!

Any help with the rules?

CM

Replies

Chris Murray
User offline. Last seen 18 years 20 weeks ago. Offline
Joined: 10 Mar 2004
Posts: 12
Groups: None
Excellent!!

Thank you very much!!!
Joao Ribeiro
User offline. Last seen 6 years 10 weeks ago. Offline
Joined: 21 Mar 2003
Posts: 64
You may check "freeze units per time period" on, but be aware that it will apply to all activities.

Cheers.