Recording progress when changes occur

5 replies [Last post]
George Bolton
User offline. Last seen 19 years 9 weeks ago. Offline
Joined: 21 Oct 2005
Posts: 11
Groups: None
Hi,

I wish to know how you deal when project is underway and you have to record the progress when new items or new job have been added to your original contract. For example, let’s take the following example:

Activity Estim. MH Weight Progress Earned
-------- --------- ------ -------- ------
Act. 1 150 15% 100% 150
Act. 2 250 25% 60% 150
Act. 3 200 20% 15% 30
Act. 4 180 18% 0% 0
Act. 5 220 22% 0% 0
--------- ------ -------- ------
Total 1000 100% 33% 330

Now, management or customer instructs you to add one more activity. Note that the Estimated Mhrs will increase, the distribution weights will change per each activity, and therefore the overall progress (based on resource) will also change (lower).

Activity Estim. MH Weight Progress Earned
-------- --------- ------ -------- ------
Act. 1 150 14% 100% 150
Act. 2 250 23% 60% 150
Act. 3 200 18% 15% 30
Act. 4 180 16% 0% 0
Act. 5 220 20% 0% 0
Act. 6 100 9% 0% 0
--------- ------ -------- ------
Total 1100 100% 30% 330

Is this right? You had 33% of overall progress before the new activity came up; now you have 30% with the new calculations. Please, let me know if I’m doing something wrong or if this ok or what approach you use. I will welcome your comments and opinions on this issue.

Thank you very much.

Replies

yousif alaubidi
User offline. Last seen 3 years 10 weeks ago. Offline
Joined: 18 Nov 2005
Posts: 55
Groups: None
Dear Edgar Ariete

Thanks
Edgar Ariete
User offline. Last seen 6 years 21 weeks ago. Offline
Joined: 17 Jul 2005
Posts: 184
Dear Yousif,

I’m trying to learn to write in Arabic but it’s all Greek to me.

Maybe you can help me with this one.


regards,

edgar
Jose Frade
User offline. Last seen 3 years 51 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None
Hello George

It is quite frequent to have new items included in contracts (normaly we call them additionals).

One option for not having them mixed is to create a subproject for each additional. Another option is to create such a structure for the database that you can separte them and measure progress independentl (as well as the overall completion)

Any way you should always make a target for each revision you issue of the plan.

In your example you are right when mentioning the overall progress goes from 33 to 30% (because your project became bigger). This changes should also be reflected in your budget and so on.


Hope to be any help for you
BR
JMFrade

Edgar Ariete
User offline. Last seen 6 years 21 weeks ago. Offline
Joined: 17 Jul 2005
Posts: 184
Hi,

I guess you are right. That’s why it’s difficult to compare your Target with your Current Plan considering your sample.

If I may add your question, How many Target Plans does a Project needs?
yousif alaubidi
User offline. Last seen 3 years 10 weeks ago. Offline
Joined: 18 Nov 2005
Posts: 55
Groups: None
Dear Edgar Ariete


If you work in any site you will see that project as actul case, so that i think our working in that program((primavera p3)) must be to find a solution for any case, and with repect to that case for updating of information after you entered a new data

..very easy ,


you can solve by enter the new percent for each acitivity as indivitual case, than enter the remainding date for each case after get schdual new , than you can see the differance

Ihope advise you by this inforamtion ,

thank you for your reponse

with best best

Engineer : Yousif A.Ayal
Iraq
Basrah
23/11/2005